|
Final Report Summary The goal simply stated is to develop a project that will improve
tidal exchange with Nantucket Sound in order to address water
quality issues (to improve marine fisheries) while protecting
environmental values, preventing and relieving flooding, and
reducing public health threats from mosquito-borne diseases. This
report reviews background information, and new field results and
analyses to form a conceptual plan for a new inlet at Rushy Marsh
Pond. The conclusion is that such an inlet is technically feasible,
could be constructed at reasonable cost, and is in principle
permittable by relevant agencies.
Part 1 of the report discusses the prevailing coastal processes
bearing on the Rushy Marsh Pond outer shore, that set limits on what
can be done, and how, with regard to the new inlet. Rushy Marsh Pond
lies on the south coast of Cape Cod in an enigmatic coastal setting
(Fig. 1) .
Historical changes in the outer shore at Rushy Marsh Pond, leading
to its present configuration, can only be understood and
accommodated in the larger context of this part of Cape Cod. Over
the past century it has been characterized simultaneously by low
tidal and wave energy, but at the same time by active changes in the
configuration of coastal landforms.
This seeming contradiction results from the unusually active tidal
inlet hydraulic processes at the neighboring mouths of Popponesset
and Cotuit Bays. The area also has an abundant offshore sediment
supply resulting from converging littoral drift of sand from the
west and from the east.
In essence, the observed history of coastal dynamics here results
from an interplay between inlet hydraulics, wave attack, and weak
littoral drift (Fig. 2). Human activities,
such as dredging (which began as early as 1896) and the construction
of groins and seawalls, are other significant factors. The natural
inlet to Rushy Marsh Pond, depicted in several historical maps,
closed a few years after an offshore island disappeared, probably
related to dredging (Fig. 3).
Over the past three decades, the principal factor involved in
evolution of the outer shoreline at Rushy Marsh Pond (loss of the
hook) has been wave overwash of barrier spit remnants, pushing the
sand into the abandoned, inactive inlet channel from Popponesset
Bay, and onto the beach behind. Wave action around the diminishing
hook caused short-term, localized erosion problems on the adjacent
outer shore during the 1970s and 1980s, but these processes have
completed their work and the present beach is now wider and more
stable than before.
Part 2 addresses environmental conditions within the Pond itself, to
identify the existing environmental issues, limits on what
improvements can be expected with increased flushing, and conditions
that will need to be addressed in engineering a suitably enhanced
opening to the sea. Materials presented here are based largely on
new field observations and calculations conducted expressly for this
study.
Rushy Marsh Pond lies in a glacial moraine landscape
(Fig. 4), in which kettle holes are variously
filled with ponds, wetlands, or are drydepending upon their
elevation, supply of water, and other factors. Rushy Marsh Pond has
an area of 14.9-acre and is up to 7.5 feet deep
(Fig. 5), with a surface-level elevation of about +2 to +3.3
feet (varying seasonally and in response to a drainage pipe through
the barrier beach). The Pond contains up to 7.5 feet of mud, organic
sand, and peat over the underlying gravelly glacial sand. During our
study Pond water was highly stained a brown-red color, preventing
light penetration beneath a few feet. This coloration is believed to
result from dissolved tannic organic matter (probably from
surrounding natural vegetation) rather than from aquatic
microorganisms. Microscopic examination of a sample of discolored
water revealed very few plankton algae. Nutrients in the pond water
are not inordinately high.
Diurnal oxygen measurements support these observations, with a daily
variation of less than 2 parts per million (ppm or mg/l) in the Pond
watersuggesting moderate to low primary productivity and ecosystem
respiration. The water is nearly fresh and usually well oxygenated
to the bottom, with little stratification of temperature. During
late summer and autumn when the pond surface elevation was low and
tides in Nantucket Sound high, flow reversed tidally in the drainage
pipe, introducing salt into the Pond. Measured salinities reached 6
parts per thousand (ca. 1/5th full-strength seawater.) During
periods of salt stratification in the Pond, bottom levels of oxygen
can become strongly reduced or entirely depleted
(Fig. 6).
Nantucket Sound water adjacent to the Pond area has a salinity of
30.5 parts per thousand and transparency exceeding 6 feet. Diurnal
oxygen variation is similar to that in the Pond (except in deep
remnants of the former channel where seaweeds accumulate). Tidal
range is typically from 1.7 to 3.4 ft. and correlates strongly with
the tide measured at Nantucket Island, except tide range is 13%
lower and a lag in high tide of 2 hours occurs.
The minimum stillwater elevation for ocean flooding across the dunes
into Rushy Marsh Pond is +5 to +6 ft., with greatest flooding
vulnerability across the sections of barrier beach at the north and
south ends. All of Rushy Marsh Pond, the lowlands to the north and
to the west, and the entire barrier beach lies within the 100-year
flood zone mapped by FEMA. In addition, all of the barrier beach is
also within the Velocity Zone, subject to storm wave activity.
Part 3 examines the technical feasibility of renewed exchange with
the sea, and examines options for the design of a structure that
would accomplish this goal. Since the closing of the Pond after
1911, there is no reason to believe an inlet would remain open at
this site without structural enhancement.
Over the years several attempts have been made to re-open the
connection to the sea, mainly for the purpose of draining the Pond
to prevent flooding of surrounding lands and roads. These efforts
have entailed a wooden flume (Fig. 7), and
pipes of various diameters and lengths. These structures have
crossed both the north and the south limbs of the barrier beach; and
all of them have failed. Their failure resulted from too small a
cross-sectional area; excessive length; inadequate engineered depth
and scouring ability; siting in areas of active sand mobility; and a
design impractical to maintain.
Nevertheless, a seasonal inlet structure is technically feasible.
The preferred option suggested herein would incorporate aspects of
successful natural and artificial inlets elsewhere: the appropriate
balance between cross-sectional area and tidal prism; a
cross-section form that promotes scouring; minimal inlet length; and
siting where sand movement is minimal and existing features can
provide shelter for the inlet channel. In addition, ease of
maintenance is an essential design factor. Finally, it should be
possible to easily close off the structure for storm surge flood
control, inlet maintenance, and water quality management purposes.
These factors would be incorporated into a new inlet sited at the
former flume location, on the south limb at Oregon Way, where an
easement for this purpose already exists.
Given the natural conditions at Rushy Marsh Pond, such an inlet
would rapidly improve the Pond as a healthy coastal salt pond
ecosystem. A restored alewife run could be expected and marine and
estuarine fishes and invertebrates would return. Plant and animal
biodiversity typical of a salt pond setting would become
reestablished. Introducing seawater would flush out the tannic water
currently filling the Pond. The new inlet would not significantly
increase flooding danger; to the contrary it would alleviate
seasonal flooding of neighboring lands and roads
Part 4 translates the above scientific and technical information
into the realm of applicable regulations and funding that will, in
the end, determine whether or not an inlet project can be built.
The overall purpose of this project is to provide environmental
information for Rushy Marsh Pond and a conceptual plan for a new
inlet to reconnect the Pond with the sea. More specifically, the
goal is to develop a project which will improve tidal exchange with
Nantucket Sound in order to address water quality issues for
enhancing marine fisheries, while protecting environmental values.
Other goals and benefits are to prevent and relieve flooding, reduce
public health threats from mosquito-borne diseases and enhance
biodiversity. Avid public support exists for such a project.
The preferred inlet option would be sited in the existing right of
way across the south limb of the barrier beach near Oregon Way
(Fig. 8). The inlet structure would consist
of an open-top sluiceway built of pre-cast concrete sections. The
sluiceway would be engineered to control or terminate flow, and to
maximize ebb-flow scouring. The sluiceway would cross from the shore
at the Pond side to the 4 MLW elevation contour location on the
Sound side, with an engineered depth of about 2 feet MLW for the
structure (Fig. 9). The unstructured channel
connecting the sluiceway and the Sound, across the beach, would be
scoured primarily by ebb flow from the Pond. A simple bridge of slab
concrete across the sluiceway would provide owners access to
adjacent private lands. This alternative out of four examined in
depth provides the multiple benefits of marine fisheries, water
quality and ecological enhancement, reduction of flooding, and
public health threats. This alternative was also deemed feasible
when analyzed under the eight feasibility factors used to assess
each alternative, i.e., goals achievement, multiple benefits,
environmental impacts/permitability, easements, capital costs,
maintenance/operations costs, safety, and potential funding sources.
This project requires several permits from agencies responsible for
the use and modification of coastal lands, wetlands, and waters. The
following permits will be required: an Order of Conditions from the
Conservation Commission, Certification from the Mass Environmental
Policy Act (MEPA) Office, a Department of Environmental Protection (DEP)
Section 401 Water Quality Certification, a DEP Ch.91 Waterways
Permit and a new license or license amendment, a Mass Coastal Zone
Management Consistency Concurrence, and a U.S. Army Corps of
Engineers Section 404 PGP 11 or individual permit. In addition, due
to agency discretionary power, a Development of Regional Impact may
be required from the Cape Cod Commission, and an Environmental
Impact Report may be required by MEPA. In conclusion, significant
difficulties will be encountered in seeking needed permits; however,
this project could be successfully implemented if arguments are
accepted to restore marine fisheries and preserve functions of flood
and storm damage control.
The cost estimate for the preferred alternative is $163,000 with
yearly maintenance and operations costs of $8,472. Possible sources
of support for the project include both technical and financial
support at the local, regional, state, and federal levels. Funding
sources include government agencies and nonprofits at all levels.
The recommended funding strategy is to combine a variety of sources.
Local non-profit funding now could be used to keep the project
momentum going by developing a preliminary design, inventorying
wetlands, completing pre-application regulatory review and
developing and applying for funds from several sources. Several
grant opportunities are now approaching and the Town should be
targeted for requests in the fall. An estimated $10,000 now would
provide the services to complete preliminary design and apply for
construction funds.
This report was produced by The Coast & Harbor Institute and Robert
L. Fultz Associates. The towns Project Monitor was Mr. Robert
Gatewood, Conservation Administrator, Town of Barnstable.
|